Data center market note

Chile's national data center plan: what PDATA promises on permits and what it does not settle about power

Chile's PDATA, presented December 5, 2024, plans a critical-permits guide, environmental criteria and a siting tool, all described in future tense. A site advisor should verify permit instruments and power delivery as two separate evidence files.

Aerial view of a data center under construction

What PDATA is, and what a tenant should conclude

Chile's National Data Center Plan 2024-2030, known as PDATA, is a permit-path and siting instrument, not evidence that any specific site is permit-ready or powered. A site-selection advisor should treat it as one of two separate diligence files: the first verifies which PDATA permit instruments actually exist today, and the second verifies an energization date backed by a connection agreement, substation and line scope. The plan announcement alone settles neither.

What the plan commits to on permits

According to the law firm Cuatrecasas, the Government of Chile presented PDATA on December 5, 2024, led by the Ministry of Science, Technology, Knowledge and Innovation in coordination with multiple ministries and entities. Cuatrecasas reports that the plan sets three key objectives: promoting investment in data centers by clarifying regulatory conditions and giving investors certainty about regulatory processes; decentralization and sustainability, connecting investment with regional capabilities; and strengthening research and development. Under the investment objective, Cuatrecasas says the plan will produce a critical-permits guide detailing the permits and regulatory processes required to build and operate data centers in Chile, plus an environmental evaluation criteria guide with standardized technical criteria to optimize environmental evaluation of data-center projects. Under the sustainability objective, Cuatrecasas reports that a digital tool will integrate information on energy availability, land use, connectivity and socio-environmental variables to identify strategic areas for installation, and that Clean Production Agreements between the state and industry will be promoted. A strategic committee will be created to monitor the industry and the plan's implementation.

What the plan summary supports, and where inference begins

The Cuatrecasas text describes these instruments in the future tense: the guides will be elaborated, the tool will be available, the committee will be created. This is Atom's reading of the source, and the inference is that an advisor should treat the critical-permits guide, the environmental criteria guide and the digital tool as planned instruments, not confirmed issued guidance, based on this document. Cuatrecasas itself notes that implementation requires careful consideration of legal and regulatory challenges and a commitment to sustainability and equity, and that companies and entities involved must be prepared to meet regulatory requirements and work closely with the state and local communities. A practical first step, proposed here as a diligence step rather than a sourced fact: ask the plan sponsor or the relevant permitting authority which PDATA instruments are final, draft or not yet issued, and obtain the current text of each. A plan announcement is a statement of intent, not proof that the guidance exists.

Why power delivery is a separate file

The clearest illustration of why permit-path evidence and power-delivery evidence are distinct categories comes from Mexico, not Chile, and it is used here as a reasoned comparison. Xataka México reports that Guillermo García Alcocer, former president of Mexico's Energy Regulatory Commission, said in an interview with Aristegui Noticias that some data centers in Querétaro have waited up to two years to connect to the electric grid, with buildings finished and equipment installed. Xataka explains the mechanism: available electricity does not automatically mean a new installation can connect, because lines, substations and equipment are needed to deliver power at the right voltage and maintain a stable supply. A substation does not generate energy; it changes voltage levels and connects parts of the network, so a lack of connection capacity can mean the existing infrastructure cannot incorporate new large loads. Xataka México, citing Diario Rotativo, also reports that the Mexican data-center association MEXDC said Querétaro concentrated 72 percent of Mexico's 279 megawatts of installed data-center capacity as of May 2026, with about 10 centers installed and 12 projects in development. The same article reports that CloudHQ announced a 4.8 billion US dollar campus of six data centers in Querétaro contemplating up to 900 megawatts of critical IT load, with its own substation of up to 900 megawatts and a 400 kilovolt transmission connection. These are a company announcement and association figures, not verified operating capacity, but they show the scale at which connection infrastructure becomes a project in itself.

The scale context a tenant should keep in mind

The International Energy Agency's special report Energy and AI, published April 2025, gives the backdrop. The IEA says data centers accounted for around 1.5 percent of global electricity consumption in 2024, or 415 terawatt-hours, and that consumption is set to more than double to around 945 terawatt-hours by 2030 in its Base Case, a forecast rather than a reported fact. The IEA also notes that AI-focused data centers can draw as much electricity as power-intensive factories such as aluminium smelters but are much more geographically concentrated, with nearly half of data-center capacity in the United States in five regional clusters. The report is global and United States-centric, not Chile-specific, but the concentration point is why local grid conditions, not national averages, decide a site.

The two-file test, as a proposed checklist

The following steps are Atom proposals for an advisor's diligence, not conclusions from the sources. File one, permits: request a permit matrix naming each approval, the authority that grants it, the applicant, current status, dependencies between approvals and the expected decision date; then map the specific project against the environmental evaluation criteria once that guide is available. File two, power: request an energization file containing the connection agreement or application, voltage and contracted capacity, substation and line scope, the responsible utility or grid operator, a committed energization date and the contingency if that date slips. A statement that electricity is available in the region is not a substitute for this file, as the Querétaro example shows.

What would change the answer

The answer changes if the PDATA guides are issued in final form with defined timelines, which would let an advisor test a site's permit path against published criteria instead of authority-by-authority requests. It also changes if a Chilean site can show a signed connection agreement with a committed energization date and named substation scope, which would move power delivery from a risk to a contract term. Conversely, a site presented as permit-ready solely by reference to PDATA, without the issued instruments or the energization file, should not be shortlisted on that basis.

Atom's position

This is a public-source diligence note, not a statement that Atom Industries is developing in Chile; Chile is not among the company's stated candidate markets. Atom Industries plans to develop AI data-center sites in Latin America, putting together firm power, a permitted site and a signed anchor customer with strong credit on a long-term take-or-pay contract before construction, so that an experienced operator can build and run each facility. Atom Industries has no site, no power contract, no customer, no selected operator and no commitments of any kind. In Atom's analysis, powered land is common; what is scarce is a site that meets a tenant's full specification in the market the tenant wants, with the anchor contract in hand, and the anchor's credit quality decides whether a project can be financed. The next question worth asking a site sponsor: which PDATA instrument, in its current issued text, does the site actually rely on, and what does the signed connection agreement say about the energization date?

Sources & further reading

This perspective supports research and relationship development. It does not represent available manufacturing capacity, a committed transaction or an investment offering.